Hi,
I am using Project 2007. I set the calendar such that resources work 8 hrs a day. However, there are days when the resource shows only 2 hrs. These days are highlighted in red in the Resource Usage view. The resources have Max Units as 100%. Can someone pls tell me the reason for this? Thanks, Preeti. |
|
![]() |
||||