Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 04-20-2014, 11:39 PM
preetsp preetsp is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2007
Novice
Resources not showing 8 hrs per day
 
Join Date: Apr 2014
Posts: 5
preetsp is on a distinguished road
Default Resources not showing 8 hrs per day

Hi,

I am using Project 2007. I set the calendar such that resources work 8 hrs a day. However, there are days when the resource shows only 2 hrs. These days are highlighted in red in the Resource Usage view.

The resources have Max Units as 100%.

Can someone pls tell me the reason for this?

Thanks,
Preeti.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resources not showing 8 hrs per day Resources pool showing file name grazi Project 2 04-04-2014 11:12 AM
Resources not showing 8 hrs per day Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Resources not showing 8 hrs per day How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Resources not showing 8 hrs per day Total Resources 602chrislys Project 1 10-04-2010 09:04 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:36 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft