Resources not showing 8 hrs per day
Hi,
I am using Project 2007. I set the calendar such that resources work 8 hrs a day. However, there are days when the resource shows only 2 hrs. These days are highlighted in red in the Resource Usage view.
The resources have Max Units as 100%.
Can someone pls tell me the reason for this?
Thanks,
Preeti.
|