Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #4  
Old 04-22-2014, 06:42 AM
JulieS JulieS is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Correct. Project says that if a resource is assigned to multiple tasks and the sum of the assignment units (Peak Units) is above the resource's maximum units - they are overallocated.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resources not showing 8 hrs per day Resources pool showing file name grazi Project 2 04-04-2014 11:12 AM
Resources not showing 8 hrs per day Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Resources not showing 8 hrs per day How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Resources not showing 8 hrs per day Total Resources 602chrislys Project 1 10-04-2010 09:04 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft