work of labor vs work of excavator
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default work of labor vs work of excavator


I am entering to my schedule work values for each task. For example I said surveying will take 10 hours, foundation formwork will take 100 hours etc... all by labor so it is fine if ms project adds them together. but how about excavating the site. it is work by excavator not human. but the work is still added to work of other tasks in the summary task. the difference will be in the hourly rate of a human labor vs an excavator, which will be much more expensive correct?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
work of labor vs work of excavator How does "fixed work" work? sofia Project 3 10-21-2013 05:30 AM
Getting macro to work kirkm Word 0 08-25-2013 05:52 PM
work of labor vs work of excavator What am I missing to get this to work? fredep57 Word VBA 1 05-04-2012 01:26 AM
Missing some work from work really need help lukepierce222 Word 6 04-19-2012 08:41 AM
work of labor vs work of excavator work vs regular work. and how regular work works user0044 Project 5 03-06-2012 07:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft