#1
|
|||
|
|||
![]()
can i assign a labor resource more than once to the same activity?
or, for every person we have, we need to have a different labor? i mean i wanted to tell ms project that an activity will have 5 labor. but couldnt do it. |
#2
|
|||
|
|||
![]()
No. Each can only be assigned to a task once. If you need more than one labor resource, either increase the resource's max. units to 200% and assign 200%, or create another resource and assign the additional resource.
|
#3
|
|||
|
|||
![]()
ok. but if i do 200% it creates a problem when leveling later as ms project will try to level it down to 100% correct?
|
#4
|
|||
|
|||
![]()
No. If you increase the max. units to 200%, the resource will not be over-allocated. Leveling is only for circumstances where Peak Units > Max. Units.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
scott.hannaford | Project | 1 | 10-21-2013 05:32 AM |
![]() |
jjmclell | Project | 2 | 12-17-2012 04:28 AM |
Which column shows just labor cost? | ketanco | Project | 9 | 06-20-2012 02:19 PM |
Assiging more than one labor of the same type | ketanco | Project | 5 | 06-08-2012 01:28 PM |
![]() |
ibclare | Office | 4 | 06-02-2011 03:22 PM |