![]() |
#1
|
|||
|
|||
![]()
Have a weird issue with project durations
Reducing Units Method If I have a task that takes 4 days (set up using defaults) - If I reduce the persons units to that task to 50% - the duration increases to 8 days - no problem with this. Calendar assignment method However I have a separate calendar for PT time staff - who only work 4 hours.If I assign this task to someone using this calendar the duration does not increase (although the end date moves) To a simple guy like me- I appear to be doing the same thing - as effectivley the hours per day are reduced from 8 to 4 in either scenario. - can anyone provide me with an explanation as to why the duration doesn't increase when I use the different calendar ? |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Project baseline duration | Alka | Project | 1 | 11-20-2012 05:09 AM |
![]() |
Joeb | Project | 3 | 06-25-2012 04:18 PM |
Tracking resources in project | new_to_project | Project | 3 | 07-06-2011 03:50 AM |
How to handle resources that have Bid on project | rrmccabe | Project | 0 | 03-21-2010 12:39 PM |
Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |