Thread
:
Project Duration for Part Time Resources
View Single Post
11-20-2012, 05:39 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Actually the math does work, but I agree - it's confusing :-)
Duration = Work/ (units * hours per day)
So, the first scenario:
8 days = 32 hours/(8 hours per day * 50%)
Second scenarion:
4 days = 32 hours/(8 hours per day * 100%)
I hope this helps.
JulieS
View Public Profile
Find all posts by JulieS