Originally Posted by JulieS View Post
Actually the math does work, but I agree - it's confusing :-)

Duration = Work/ (units * hours per day)

So, the first scenario:

8 days = 32 hours/(8 hours per day * 50%)

Second scenarion:

4 days = 32 hours/(8 hours per day * 100%)

I hope this helps.
Thank you Julie,

But in the second scenario the person is only working 4 hours per day not 8. In my humble opinon it should revise the duration to 8 days

8d X 4h = 32 hours