Quote:
Originally Posted by JulieS
Actually the math does work, but I agree - it's confusing :-)
Duration = Work/ (units * hours per day)
So, the first scenario:
8 days = 32 hours/(8 hours per day * 50%)
Second scenarion:
4 days = 32 hours/(8 hours per day * 100%)
I hope this helps.
|
Thank you Julie,
But in the second scenario the person is only working 4 hours per day not 8. In my humble opinon it should revise the duration to 8 days
8d X 4h = 32 hours