Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 02-25-2012, 11:27 AM
JulieS JulieS is offline overtime work effecting task duration Windows 7 64bit overtime work effecting task duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It sounds like you are not really using the Overtime Work field -- just increasing a resource's hours per day?



If you are using Overtime, you have to assignment it to the task specifically. Increasing the number of hours the resource is scheduled (in the Task Usage or Resource Usage view) just increases assignment units.

You are correct, assignment units over 100% means that the resource can create more than 8 hours of work (effort) in an 8 hour duration.

Decreasing task duration means the finish date moves in (earlier). If you start moving the finish date of tasks in then you might be able to finish the project earlier.
Reply With Quote
  #2  
Old 02-26-2012, 08:03 AM
user0044 user0044 is offline overtime work effecting task duration Windows XP overtime work effecting task duration Office 2012
Novice
overtime work effecting task duration
 
Join Date: Feb 2012
Posts: 9
user0044 is on a distinguished road
Default

Hi JulieS

No, I am changing a value Overtime work column in the Resource Usage View and this is effecting the task duration.

please guide in this regard

thanks
Reply With Quote
  #3  
Old 02-27-2012, 06:29 AM
JulieS JulieS is offline overtime work effecting task duration Windows 7 64bit overtime work effecting task duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

As I explained, overtime work always decreases duration -- however it should not be changing assignment units.

Perhaps if you tell me what you want to accomplish, I can be of more help. But again, assigning overtime work will change the task duration.
Reply With Quote
Reply

Tags
overtime work



Similar Threads
Thread Thread Starter Forum Replies Last Post
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM
overtime work effecting task duration Task cannot stop once started, but cannot continue into non-work hours sullied Project 3 12-05-2011 06:32 PM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Work as percent of another task JohnG10 Project 0 12-10-2010 07:51 AM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:07 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft