Thread
: [Solved]
overtime work effecting task duration
View Single Post
02-25-2012, 07:49 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Assigning overtime work always drops the duration of tasks. The amount of overtime is deducted from the total work on the task and the lower number is used to recalculate duration. Overtime is considered "off the working calendar".
JulieS