Old 02-25-2012, 11:27 AM
JulieS JulieS is offline overtime work effecting task duration Windows 7 64bit overtime work effecting task duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It sounds like you are not really using the Overtime Work field -- just increasing a resource's hours per day?

If you are using Overtime, you have to assignment it to the task specifically. Increasing the number of hours the resource is scheduled (in the Task Usage or Resource Usage view) just increases assignment units.

You are correct, assignment units over 100% means that the resource can create more than 8 hours of work (effort) in an 8 hour duration.

Decreasing task duration means the finish date moves in (earlier). If you start moving the finish date of tasks in then you might be able to finish the project earlier.
Reply With Quote
 

Tags
overtime work

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM
overtime work effecting task duration Task cannot stop once started, but cannot continue into non-work hours sullied Project 3 12-05-2011 06:32 PM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Work as percent of another task JohnG10 Project 0 12-10-2010 07:51 AM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft