![]() |
|
#3
|
|||
|
|||
|
I'll try that out...that should do the trick. What about a situation where a task cannot be stopped once started, cannot go into non-work hours, but doesn't have to start at 8am. For instance, I have a 4 hour task with only 3 hours left in the day, I could use what you described to force it to start the next day at 8am. However, what if the schedule shifts later and then the opening goes to 5 hours in the day. I can now complete that task within that day, but this method would force it to start the next day at 8am no matter what. Isn't there just a way to have Project stop putting tasks on hold during non-work hours and only schedule it if there is enough time in the workday?
Thanks a lot! Rob |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Work Week: hours vary each day
|
rkc | Outlook | 1 | 08-31-2011 01:17 PM |
| Work as percent of another task | JohnG10 | Project | 0 | 12-10-2010 07:51 AM |
| Stop the % Complete of subatasks from counting against the Main task | bzeyger | Project | 0 | 06-08-2010 06:19 AM |
Need urgent help .. lost 6 hours of work .. assignments due in tomorrow
|
Phatmat | Word | 1 | 10-15-2009 08:38 AM |
| Need Help Getting Started, Please. Thanks | ChunkyZergling | Outlook | 1 | 04-24-2009 07:38 AM |