sullied sullied is offline Task cannot stop once started, but cannot continue into non-work hours Windows 7 64bit Task cannot stop once started, but cannot continue into non-work hours Office 2010 64bit
Novice
Task cannot stop once started, but cannot continue into non-work hours
 
Join Date: Dec 2011
Posts: 3
sullied is on a distinguished road
Default

I'll try that out...that should do the trick. What about a situation where a task cannot be stopped once started, cannot go into non-work hours, but doesn't have to start at 8am. For instance, I have a 4 hour task with only 3 hours left in the day, I could use what you described to force it to start the next day at 8am. However, what if the schedule shifts later and then the opening goes to 5 hours in the day. I can now complete that task within that day, but this method would force it to start the next day at 8am no matter what. Isn't there just a way to have Project stop putting tasks on hold during non-work hours and only schedule it if there is enough time in the workday?



Thanks a lot!
Rob
Reply With Quote
  #2  
Old 12-05-2011, 06:32 PM
JulieS JulieS is offline Task cannot stop once started, but cannot continue into non-work hours Windows 7 64bit Task cannot stop once started, but cannot continue into non-work hours Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Rob,

If the task is only 3 hours in duration, then it can start as late as 2:00 pm assuming a 5:00 pm finish date -- create an additional task calendar where the only working time allowed is from 7:59 am to 1:59 pm.

There is no automatic way to have Project not split a task over non-working time.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Task cannot stop once started, but cannot continue into non-work hours Work Week: hours vary each day rkc Outlook 1 08-31-2011 01:17 PM
Work as percent of another task JohnG10 Project 0 12-10-2010 07:51 AM
Stop the % Complete of subatasks from counting against the Main task bzeyger Project 0 06-08-2010 06:19 AM
Task cannot stop once started, but cannot continue into non-work hours Need urgent help .. lost 6 hours of work .. assignments due in tomorrow Phatmat Word 1 10-15-2009 08:38 AM
Need Help Getting Started, Please. Thanks ChunkyZergling Outlook 1 04-24-2009 07:38 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:03 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft