Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

I tried the first solution, but since the people have more tasks in the same period assigned them, to put them as 100% per task has a result of people shown as overloaded in the resources diagram, I thought there is a simpler solution in Project for that...
Im sure Im not the only one having the issue that people assigned to projects do accutualy as well other things than to work only on the project... but this is more a topic of accurate planning and as well about a conflict of theory and praxis
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Reporting ManDays on people not fully assigned to the Project Converting Powerpoint into Fully Accessable PDFs KCD123 PowerPoint 4 09-28-2011 10:03 AM
Hyperlink assigned sounds do not play Starscream PowerPoint 0 03-08-2011 02:14 PM
Resource Overallocation Reporting Mutso Project 0 11-05-2010 12:27 PM
Reporting ManDays on people not fully assigned to the Project Outlook 2007 Not Fully Closing LabanM Outlook 1 09-28-2010 02:27 PM
Project Reporting vickib1 Project 0 09-08-2010 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:07 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft