Hi
Project will only report on planned and actual assignment durations. It cannot report anything in between.
As I suggested earlier you can export assignment information to Excel and then in nthe Start and Finish columns in Excel you can change the date format so that it reports on the day only and not the time.
Hope this helps.
Good luck.
Tony (OTPM)