OK may be I express my self wrong...
One thing is and that is what I need to see how much time one accualy spends on the project, that I can find in the team view...
Second thing is for internal reasons all the people contributing to the project are reported as fully assigned. That means if his task start at the 1.11. and ends on 15.11. even he is assined only for 5% and works on the task few hours, I need a report showing that he worked two weeks, in this case 10 Mandays.
|