#1
|
|||
|
|||
![]() How do I make a project schedule when we work with 2 shifts in a day? What do I have to do?? • Do I have to put in the Project settings that we have a working week of 80 hours with working days of 8 hours • Or do I have to make 2 calendars (morning and evening) with working hours from 6 a.m. to 2 p.m. and from 2 p.m. to 10 p.m.? • Or should I use both options?? • Or ……. What is the standard solution for this? Thanks in advance for thinking along ☺️ |
![]() |
|
![]() |
||||