![]() |
|
|
|
#1
|
|||
|
|||
|
How do I make a project schedule when we work with 2 shifts in a day?
What do I have to do?? • Do I have to put in the Project settings that we have a working week of 80 hours with working days of 8 hours • Or do I have to make 2 calendars (morning and evening) with working hours from 6 a.m. to 2 p.m. and from 2 p.m. to 10 p.m.? • Or should I use both options?? • Or ……. What is the standard solution for this? Thanks in advance for thinking along ☺️ |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Help with Setting 4 (10) Hour Shifts | dondiposton | Project | 1 | 03-31-2021 11:45 PM |
| 12 hour shifts 2 shifts per day 7pm-7am - problems | Patches37 | Project | 0 | 01-05-2018 02:02 PM |
| Spreading a project over two shifts | bluphoto | Project | 1 | 08-21-2015 01:27 PM |
| 12 hour work days (shifts) | John Franklin | Project | 22 | 11-12-2013 03:19 PM |
Work Offline Setting
|
thomas34461 | Outlook | 1 | 04-04-2011 01:42 PM |