ProjectPlanner ProjectPlanner is offline Earned Value isn't recalculated by MS Project Windows 10 Earned Value isn't recalculated by MS Project Office 2019
Advanced Beginner
 
Join Date: Mar 2021
Location: UK
Posts: 75
ProjectPlanner is on a distinguished road
Default

Ilya,

I also encountered the same problem when I replicated the physical % import either through Excel or XML.

Unfortunately, I don't know what is causing it but a workaround is to add a new Cost custom field, say Cost1 & rename it Calculated BCWP and enter the following formula.

[Baseline Cost]*[Physical % Complete]/100

and for "calculation for task and group summary rows", select Rollup: Sum.

Hide the default BCWP and display the Calculated BCWP field and it will work with both Excel import and manual update.

=jerome
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Earned Value Calculations - BCWP In Microsoft Project Lenin Project 0 03-25-2016 09:20 AM
Earned Value isn't recalculated by MS Project Microsoft Project Managing Planned / Earned Value & Actual Costs shane_dav71 Project 1 10-06-2014 06:07 PM
Earned Value isn't recalculated by MS Project MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
earned value not calculating ketanco Project 3 08-16-2012 02:13 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:06 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft