![]() |
#2
|
||||
|
||||
![]()
Ilya,
I also encountered the same problem when I replicated the physical % import either through Excel or XML. Unfortunately, I don't know what is causing it but a workaround is to add a new Cost custom field, say Cost1 & rename it Calculated BCWP and enter the following formula. [Baseline Cost]*[Physical % Complete]/100 and for "calculation for task and group summary rows", select Rollup: Sum. Hide the default BCWP and display the Calculated BCWP field and it will work with both Excel import and manual update. =jerome |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Earned Value Calculations - BCWP In Microsoft Project | Lenin | Project | 0 | 03-25-2016 09:20 AM |
![]() |
shane_dav71 | Project | 1 | 10-06-2014 06:07 PM |
![]() |
mtbtomo | Project | 1 | 10-23-2013 06:49 AM |
Finding Earned Values for Different Baselines in a single project | pratik6312 | Project | 1 | 08-22-2013 11:18 AM |
earned value not calculating | ketanco | Project | 3 | 08-16-2012 02:13 PM |