earned value not calculating
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default earned value not calculating

hello,
in my schedule i have tasks which i assigned fixed costs. in the task usage view, the cost and cumulative cost are showing, between the corresponding start and finish dates.

1-BCWP and BCWS rows are not showing anything though. (although I also have a baseline). i checked both the current start and finish dates interval and the basleine start and finish dates interval but no BCWS and BCWP is visible. Why?

2-lets say I wanted to know the EV for last month, July. If it showed BCWP, I would simply add the values of BCWP for the interval of July 1- July 31 right?

3-BCWP would add up to fixed cost and would show between current start and finish dates of that activity correct?



4-BCWS would also add up to fixed cost but it would show between basline start and finish of that activity correct?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
earned value not calculating Calculating earned value ketanco Project 3 08-13-2012 09:06 AM
Calculating Profits? MarkL Project 1 06-12-2012 07:19 AM
earned value not calculating Calculating age at date jamierbooth Excel 2 02-22-2011 03:35 AM
earned value not calculating How to apply budget for earned value analysis ttorneby Project 2 06-03-2010 04:52 PM
Good commission to be earned for writing some office questions iqnetsys Office 0 02-23-2009 05:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:36 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft