Old 08-15-2012, 10:32 AM
ketanco ketanco is offline updating task progress Windows 7 64bit updating task progress Office 2007
Expert
updating task progress
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default updating task progress


when i was updating a task (and the current day i set to today which is august 15th) the task start date was august 2 and finish date was showing august 6th but that task is 50% complete. so the task that is not yet done can not finish in the past. so i selected the task and went to tools>tracking>update project and then selected update work as complete through, set 0-100 complete and marked selected tasks. but it did not bring the task to current date and then made it 100 % which i dont want. so i made it 50% again also tried making the remaining duration so that it will be 50% but the question is why it doesnt bring the task to current date? it still makes it finish in the past. shouldnt it automatically lengthen the actual duration because it knows the current date is august 15 now.
Reply With Quote
  #2  
Old 08-16-2012, 05:09 AM
JulieS JulieS is offline updating task progress Windows 7 64bit updating task progress Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

So was the task 50% complete back in early August or is it 50% complete this week?

If it was 50% complete in early August:
  1. Set if 50% complete
  2. Tools > Tracking Update Project > Reschedule uncompleted work to start after August 15th.

The task will split with the portion that was 50% complete staying back in early August and the remaining work and duration will be rescheduled to commence on August 15.

If no work was done back in early August, then do step 2 only to reschedule the entire task to begin on August 15th
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to create a progress bar AfterLife6 Excel 1 07-31-2012 08:43 PM
updating task progress Update Progress breaks with constraint benwimpory Project 1 03-14-2012 08:44 AM
updating task progress arrows remain between task bars, but predecessor info disappears from task info Antares Project 1 12-14-2011 09:19 AM
Updating Links johnp Word 0 10-18-2011 03:36 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:45 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft