  #2  
Old 12-16-2015, 09:35 AM
Margaret Pate Margaret Pate is offline Baseline versus actual data Windows 10 Baseline versus actual data Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Hi,

Have you got the "updating task status, updates resource status" option checked? This may be causing the problem if you are using resources.

The way round it for the tasks is to, from the task usage view: -

1. Add the actual start date to the table and enter the actual start date.
2. On the right hand side, add the actual work row and add the actual work on the right hand side
3. Delete any future work from the work row, ie: remaining work =0
4. Set the actual finish date.

This works for me so hopefully it will help you.

Regards,

Margaret
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Actual working hours per day climbatron Project 2 12-17-2015 03:13 PM
Baseline versus actual data Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
outlook versus outlook express craig1000 Outlook 0 04-07-2010 01:52 PM
Baseline versus actual data Print preview and actual print do not match? anthrax19888 Word 1 10-12-2009 08:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft