Thanks Julie for the reply.
The resources calendar shows availability during this time. Also when I add this resource to another fixed duration task during the same timeframe there is no error on the task. |
|
#2
|
|||
|
|||
|
Okay - let's try a bit more information. You mention that the resource is assigned to another task that overlaps. Are you creating a resource overallocation? Is your leveling set to automatic? What is the peak unit for the resource's during the overlap? What is the resource's max units?
Can you attach a picture or perhaps the file? |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Levelling resource's units to calculate duration task
|
codeghi | Project | 10 | 03-01-2014 08:13 AM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly
|
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
|
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
How to use fixed duration, fixed work and have resources/units leveled automatically?
|
Joeb | Project | 3 | 06-25-2012 04:18 PM |
| Task duration between 2 fixed milestones | cettolox | Project | 3 | 01-24-2012 06:33 AM |