  #3  
Old 01-11-2017, 11:03 PM
Andy Francis Andy Francis is offline physical % complete Windows 8 physical % complete Office 2003
Novice
physical % complete
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default physical % complete

Hi Julie, we are using a standard Level of Effort ( as a rule of credit) for the activity. What i cant fathom out is if I have loaded the work hrs for the project duration 10000. I have then progressed the phys % from 0 to 2%. I would of expected the actual No of hrs to = 1000/2% = 200 hrs. what the actual is showing me is 196hrs. which is giving me a false EVM calcuation.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
physical % complete How to show planned% complete and actual% complete on the (Project Overview) dashboard report? zislam14 Project 3 12-17-2015 03:03 PM
physical % complete physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
physical % complete project for projected vs physical theWizardAKQ Project 3 01-24-2014 06:16 AM
physical % complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:26 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft