Hi Julie, we are using a standard Level of Effort ( as a rule of credit) for the activity. What i cant fathom out is if I have loaded the work hrs for the project duration 10000. I have then progressed the phys % from 0 to 2%. I would of expected the actual No of hrs to = 1000/2% = 200 hrs. what the actual is showing me is 196hrs. which is giving me a false EVM calcuation. |
|
#2
|
|||
|
|||
|
I'm not sure that the Physical % complete ties in with actual work values. The Earned Value is either calculated from % complete (duration) or physical % complete - but not % work complete. When I create a simple project and set things up to use Physical % complete as the earned value method (both the field and the calculation), updating Physical % complete has no effect on Actual Work. The actual work values remain zero.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to show planned% complete and actual% complete on the (Project Overview) dashboard report?
|
zislam14 | Project | 3 | 12-17-2015 03:03 PM |
physical complete %, regular work, vs % complete
|
ketanco | Project | 1 | 06-16-2014 11:08 AM |
| Physical % Complete and Task Duration | ChuckM | Project | 3 | 02-09-2014 09:21 AM |
project for projected vs physical
|
theWizardAKQ | Project | 3 | 01-24-2014 06:16 AM |
complete % and physical complete %
|
ketanco | Project | 3 | 05-25-2012 08:19 AM |