Hello Julies,
I discovered the problem.
Open the "Master.mpp", click on "Resource Pool->Share Resources...": the default setting on conflict with calendar or resource information is "Sharer takes precedence".
I had to click on "Pool takes precedence" to resolve the problem.
Regards.
Luca
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Problem with non-working days in MP2013 reminder for every 15 working days araamuthan Outlook 1 03-25-2015 11:49 PM
reminder for every 15 working days araamuthan Excel 0 03-25-2015 06:49 AM
Maximum number of working days reached= warning color perZZon Excel Programming 1 05-09-2014 03:01 PM
Master Projects with different Working Days Philip.Skeet Project 2 08-19-2011 09:45 AM
Problem with non-working days in MP2013 Non-Working Days on Gantt JayTT Project 1 01-28-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:23 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft