![]() |
|
|
|
#1
|
|||
|
|||
|
Hi Guys,
I was wondering whether MS Project 2010 has the ability to include multiple sub projects within a master project all with separate scheduled working weeks/times. I have set some of the projects up as individual projects (7d working week & 24 hr day ops) and they are fine, however once I import them they are being transferred into the default standard working week of 8 hrs/d & 5 days/week. Can anyone shed any light on this? Cheers Phil |
|
#2
|
|||
|
|||
|
Hi Phil
You would need to setup a different calendar in your Master Project File for each sub project and then assign the relevant calendar to each sub project. Hope that helps. Good luck. Tony(OTPM) |
|
#3
|
|||
|
|||
|
If you INSERT instead of IMPORT the subprojects, they will only be links to the real project plans, and will retain their original calendars.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Merging Projects | C_Howard | Project | 2 | 03-29-2012 02:00 PM |
Non-Working Days on Gantt
|
JayTT | Project | 1 | 01-28-2011 05:42 AM |
| Linking tasks between projects error | clear2pay | Project | 0 | 12-05-2010 06:46 PM |
| How do i implement learnings from completed projects? | stingy | Project | 0 | 03-18-2010 02:09 AM |
| Writing code with C# and VB.NET to create Outlook add-ins and other projects | kistou | Outlook | 0 | 01-13-2010 04:23 AM |