When I open Task1.mpp and choose "Open Resource Pool" I see the assignment for Luke starting on 6/10 and ending on 6/21 for the Congress task. He is not scheduled to work from June 13 - 16.

When you open Task1 are you opening the pool file? Tested using Project 2013 version: 15.0.4823.1000