#1
|
|||
|
|||
![]()
HI all,
I have set up a Master Project file with a series of sub project files linked into it. I also have a resource pool which my sub projects are linked too. I am looking to add our company-wide (and national holidays) to a Master Project file so show non-working time across all my sub-project. I have tried to add these holidays to my Master Project file via the Change Working Time/ Exceptions settings. However, this doesn't seem to work. Could someone explain how I can add these holidays to my Master file to allow me to see these as non-working time across my sub-projects? Thanks in advance Kind regards Barry ![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Microsoft Project holiday integration | jeccles123 | Project | 4 | 03-22-2015 01:42 PM |
Search and replace/insert HTML code into Master File using tags | dave8555 | Excel | 2 | 02-23-2014 03:51 PM |
![]() |
pmjunkie | Project | 3 | 12-14-2011 09:08 AM |
Outlook 2003 calander starts in holiday list mode | kc_guy | Outlook | 0 | 02-09-2011 07:36 AM |
Panic Adding slide numbers to master | Roscoe | PowerPoint | 0 | 01-26-2011 12:36 PM |