HI all,
I have set up a Master Project file with a series of sub project files linked into it. I also have a resource pool which my sub projects are linked too.
I am looking to add our company-wide (and national holidays) to a Master Project file so show non-working time across all my sub-project.
I have tried to add these holidays to my Master Project file via the Change Working Time/ Exceptions settings. However, this doesn't seem to work.
Could someone explain how I can add these holidays to my Master file to allow me to see these as non-working time across my sub-projects?
Thanks in advance
Kind regards
Barry