Thread
: [Solved]
Adding national holiday to Master File
View Single Post
03-21-2016, 06:56 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
The edits need to be made to the subproject files. The master project is not doing any scheduling - just displaying. But you can edit one calendar and then copy that to each other subproject.