  #7  
Old 01-07-2016, 06:55 AM
Margaret Pate Margaret Pate is offline Tasks with different durations to all finish on specific date Windows 10 Tasks with different durations to all finish on specific date Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Hi,

Just had a quick look at your plan, the Phase 2 milestone wont move earlier because of the dependency on Phase 1 as well as the constraints that have been set. It works fine if you are pushing the date out in the plan.

This suggests that the dependency should be the other way round and that Phase 1 should be on a fs with Phase 2. Eg. Task 3 has a predecessor 7fs-10d.

In summary, I suggest that you remove the constraints and the amend the dependency to make Phase 1 dependent on Phase 2.

Hope this helps.

Margaret
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks with different durations to all finish on specific date How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Tasks with different durations to all finish on specific date Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
Tasks with different durations to all finish on specific date % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft