![]() |
|
#1
|
|||
|
|||
![]()
Hi,
Just had a quick look at your plan, the Phase 2 milestone wont move earlier because of the dependency on Phase 1 as well as the constraints that have been set. It works fine if you are pushing the date out in the plan. This suggests that the dependency should be the other way round and that Phase 1 should be on a fs with Phase 2. Eg. Task 3 has a predecessor 7fs-10d. In summary, I suggest that you remove the constraints and the amend the dependency to make Phase 1 dependent on Phase 2. Hope this helps. Margaret |
#2
|
|||
|
|||
![]()
Thank you Margaret, I gave it a try but unfortunately not with much success.
Maybe I misunderstood what you said. I am confused how I can at the same time link phase 2 with my milestone, link phase 1 with phase 2 and also make sure that all the phase subtasks keep their "sequential" order. I attach a picture and mpp, is this what you mean? many thanks for all your help! Nantia |
#3
|
|||
|
|||
![]()
Hope I haven't misunderstood what you are trying to do - I have attached what I meant with a before and after picture.
Regards, Margaret |
#4
|
|||
|
|||
![]()
I cant thank you enough Margaret, I do understand now!
One last question please, is there a "clever" way to calculate the optimal lag period? Ideally in my project, all tasks should be sequential with no delay between them. So when we say that task 4 ('Pre-check') has dependency '7fs-10d' then this means that task 7 (phase 2) can start 10 days after task 4 has finished, correct? Does it make sense to have a different lag period per server depending on the duration of phase 1? Or the lag period should not be related at all with the actual duration of the tasks of phase 1? Apologies for the multiple questions, I am newbie and I am struggling a lot! Thanks a lot! Nantia |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
zislam14 | Project | 1 | 12-17-2015 03:58 PM |
![]() |
Rowey | Project | 5 | 05-01-2015 07:22 AM |
![]() |
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |