Tasks with different durations to all finish on specific date
View Single Post
12-16-2015, 09:24 AM
Margaret Pate
Windows 10
Office 2013
Novice
Join Date: Dec 2015
Posts: 12
Hi,
One suggestion would be to create a milestone at the top and link it to Subtask1b, etc. on a finish/finish constraint. Then you would only need to change the date for the driving milestone.
Margaret Pate