Margaret Pate Margaret Pate is offline Tasks with different durations to all finish on specific date Windows 10 Tasks with different durations to all finish on specific date Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Hi,

One suggestion would be to create a milestone at the top and link it to Subtask1b, etc. on a finish/finish constraint. Then you would only need to change the date for the driving milestone.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks with different durations to all finish on specific date How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Tasks with different durations to all finish on specific date Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
Tasks with different durations to all finish on specific date % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft