Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #3  
Old 09-17-2015, 05:07 PM
raminraiszadeh raminraiszadeh is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Novice
Start date of successor task does not change
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default

Hi Julie,

Let's say I have 100 tasks which are all linked. If I increase the duration of task #1 by 5 days, I would like the Finish Date of task #100 to be pushed back by 5 days as well. However, if task #20 is 10% complete, it causes problems.

Regarding your second question, are you referring to the (Options, Schedule) option called "Split in-progress tasks"? If so, the option is checked.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Start date of successor task does not change seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM
Start date of successor task does not change Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:07 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft