What are the links between your tasks Finish to Start? Start to Start? If everything is linked Finish to Start AND the tasks are autoscheduled AND you have split in progress selected even if task 20 has an actual start date (before its predecessor finished) and remaining part of the task should still be honoring the F to S link.