when you use split window or the task information field appears, i can see the predecessor information but not the successor informationl. is there a way to see that too?
|
#2
|
|||
|
|||
![]()
Right click in the Task form to show the shortcut menu. Select Predecessors and Successors to display both.
|
![]() |
|
![]() |
||||