How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?
Hi,
'% Complete' is auto-calculated in MS Project Professional 2013. If I update '% Complete' for a task in SharePoint 2013 to 75% and then if I open the task list in MS Project Professional 2013, then the '% Complete' is auto-calculated to 99% which is different than the one in SharePoint 2013 ie 75%.
How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013 so that '% Complete' value remains the same for a particular task in SharePoint 2013 & MS Project Professional 2013?
Please provide solution for this issue ASAP.
Your reply will be greatly appreciated.
Thanks in advance.
|