#1
|
|||
|
|||
![]()
I have recently upgraded to Project 2013 and have added resources to tasks, which are now showing on the Gantt chart next to the bar. I have tried editing Bar Styles - expecting to find Resource Names in the Text Label part of the Bar Styles box - but there is nothing there. Does any one know how to remove the resource names in 2013 Pro?
Looking forward to your assistance, Nick. |
#2
|
|||
|
|||
![]()
Hi Nick,
It hasn't changed from previous versions. Ensure you have the "Task" bar selected. You'll also need to repeat if you are using Manual tasks. I hope this helps. Julie |
![]() |
|
![]() |
||||