Question How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013?

Hi,

'% Complete' is auto-calculated in MS Project Professional 2013. If I update '% Complete' for a task in SharePoint 2013 to 75% and then if I open the task list in MS Project Professional 2013, then the '% Complete' is auto-calculated to 99% which is different than the one in SharePoint 2013 ie 75%.

How to prevent the auto-calculation of the '% Complete' field in MS Project Professional 2013 so that '% Complete' value remains the same for a particular task in SharePoint 2013 & MS Project Professional 2013?

Please provide solution for this issue ASAP.

Your reply will be greatly appreciated.

Thanks in advance.