JulieS JulieS is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 7 64bit [Project 2013] More accuracy with resource, unit %, and cost? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default


What is your setting in Resource Leveling Options? If it is set to "hour by hour" or worse yet "minute by minute" then the resource IS overallocated. Change it to day by day (at a minimum) and see if that does not resolve the overallocation. Also, what are the max units for the resource?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Remove resource name from Gannt Bar in Project Professional 2013? nick@johansens.eu Project 1 10-16-2014 05:58 AM
[Project 2013] More accuracy with resource, unit %, and cost? How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
[Project 2013] More accuracy with resource, unit %, and cost? Need totoal cost despite project being in progress Sognamed Project 1 07-23-2013 06:06 AM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:46 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft