JulieS JulieS is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 7 64bit [Project 2013] More accuracy with resource, unit %, and cost? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can assign resources at less than 100% to indicate that the resource doesn't generate the 10 hours of work per day - there are other things that take away from the "productive" time.
For example, you have a task that has a work budget of 50 hours - original duration 5 -10 hour days. But during a given week (5 days) the resource can only 8 hours of work per day. So in a duration of 50 hours, the resource can only generate 80% or 40 hours of work. If the task really is 50 hours of work, the duration will be 6.25 days.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Remove resource name from Gannt Bar in Project Professional 2013? nick@johansens.eu Project 1 10-16-2014 05:58 AM
[Project 2013] More accuracy with resource, unit %, and cost? How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
[Project 2013] More accuracy with resource, unit %, and cost? Need totoal cost despite project being in progress Sognamed Project 1 07-23-2013 06:06 AM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft