#1
|
|||
|
|||
|
I am currently developing a turnaround plan using MS Project 2013 and I am having difficulties creating a 3 shift look ahead. I need to have the 3 shift look ahead report to work with my milestones. Is there anyway possible that will allow me to create this type of report using multiple milestones so I can provide my field foreman on priority work? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
2 Shift - Project Calendar
|
Mav | Project | 1 | 09-08-2014 10:42 AM |
Noob here - I need a shift calendar by days with count of shift.
|
freeman | Excel | 8 | 09-12-2012 08:45 AM |
| Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
| Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
| Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |