MS Project 2013_3 Shift Look ahead
View Single Post
11-23-2014, 05:25 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
If I understand you correctly, you want a custom filter for tasks that are scheduled to finish in the next 36 hours? You're going to have to create a custom filter to look ahead 36 hours.