MS Project 2013_3 Shift Look ahead
I am currently developing a turnaround plan using MS Project 2013 and I am having difficulties creating a 3 shift look ahead. I need to have the 3 shift look ahead report to work with my milestones. Is there anyway possible that will allow me to create this type of report using multiple milestones so I can provide my field foreman on priority work?
|