Exclamation Effective Resourcing Management in Ms Project 2013 – A Case Study (Help needed)

In Below Scenario, i am trying to faced a situation which i could not solve ! Need assistance from you all !
Step1:
I have created a task “Paint the wall” and expecting this work to be completed in 24 hrs.
TaskName: Paint the wall
Work: 24 hrs
Task Mode: Auto Schedule.
Start Date: Jan 7, 2015 (wednesday)
Step2:
Here, i have added 3 resources
Resource1 (with max unit = 50%)
Resource2 (with max unit = 50%)
Resource3 (with max unit = 25%)
By this, i expect, Resource1 to work only 4 hrs per day. Resource2 to work only 4 hrs per day. Resource3 to work only 2 hrs per day.
Step3:
In Project Calendar, i have added non-working days for Resource 3 as Jan 8 and Jan 9.
Step4:
I assigned all 3 resources against the task “Paint the wall”, but i found that, resources efforts didn’t came as expected !
i got resource1 with 9.6hrs, resource2 with 9.6hr, resource with 4.8hr and task end date as Jan 13th 2015 !!


Expectation:
On Jan 7th, 2015 – i expected all 3 resources work. Hence total hours is 4+4+2 = 10 hrs
On Jan 8th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 4+4 = 8 hrs
On Jan 9th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 3+3 = 6 hrs
So i would expect the work to be showing as completed by Jan 9th. But it shows project will complete by Jan 13th only ! I expect project should complete by Jan 9th itself, with resource 1 using 4+4+3 = 11 hrs, resources2 also using 11 hrs and resource 3 using 2 hours only ! But i am not getting this result.
Please assist. I am using microsoft project 2013 software.




Kumar
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Master and Sub Project Management OTPM Project 12 06-15-2016 01:54 AM
Documents publish from a content management system with the wrong fonts after upgrading to Word 2013 EditorMargaret Word 3 12-04-2014 12:17 PM
Stability in Project 2007 and resourcing Guloluseus Project 3 05-13-2013 09:54 AM
Hellp needed on office Project bedawee_zeus Project 1 02-13-2012 05:41 PM
From all UPPER CASE to Proper Case davers Word 1 04-30-2009 12:41 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft