![]() |
|
|
Thread Tools | Display Modes |
#1
|
|||
|
|||
![]()
In Below Scenario, i am trying to faced a situation which i could not solve ! Need assistance from you all !
Step1: I have created a task “Paint the wall” and expecting this work to be completed in 24 hrs. TaskName: Paint the wall Work: 24 hrs Task Mode: Auto Schedule. Start Date: Jan 7, 2015 (wednesday) Step2: Here, i have added 3 resources Resource1 (with max unit = 50%) Resource2 (with max unit = 50%) Resource3 (with max unit = 25%) By this, i expect, Resource1 to work only 4 hrs per day. Resource2 to work only 4 hrs per day. Resource3 to work only 2 hrs per day. Step3: In Project Calendar, i have added non-working days for Resource 3 as Jan 8 and Jan 9. Step4: I assigned all 3 resources against the task “Paint the wall”, but i found that, resources efforts didn’t came as expected ! i got resource1 with 9.6hrs, resource2 with 9.6hr, resource with 4.8hr and task end date as Jan 13th 2015 !! Expectation: On Jan 7th, 2015 – i expected all 3 resources work. Hence total hours is 4+4+2 = 10 hrs On Jan 8th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 4+4 = 8 hrs On Jan 9th, 2015 – Since resource3 cant work, Resource1 and Resoure2 will work 3+3 = 6 hrs So i would expect the work to be showing as completed by Jan 9th. But it shows project will complete by Jan 13th only ! I expect project should complete by Jan 9th itself, with resource 1 using 4+4+3 = 11 hrs, resources2 also using 11 hrs and resource 3 using 2 hours only ! But i am not getting this result. Please assist. I am using microsoft project 2013 software. Kumar |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
OTPM | Project | 12 | 06-15-2016 01:54 AM |
Documents publish from a content management system with the wrong fonts after upgrading to Word 2013 | EditorMargaret | Word | 3 | 12-04-2014 12:17 PM |
Stability in Project 2007 and resourcing | Guloluseus | Project | 3 | 05-13-2013 09:54 AM |
![]() |
bedawee_zeus | Project | 1 | 02-13-2012 05:41 PM |
![]() |
davers | Word | 1 | 04-30-2009 12:41 PM |