JulieS JulieS is offline % completion changes finish date? Windows 7 64bit % completion changes finish date? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have your project scheduled from a fixed finish date. So all of your summary tasks constraints are As Late as Possible. When added progress, I immediately got a warning from the Planning Wizard about constraints.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Assigning finish date to work with %complete Guloluseus Project 3 12-12-2013 10:16 AM
% completion changes finish date? how to calculate backwards from a set finish date ketanco Project 1 02-07-2013 06:50 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft