![]() |
|
|
|
#1
|
|||
|
|||
|
You have your project scheduled from a fixed finish date. So all of your summary tasks constraints are As Late as Possible. When added progress, I immediately got a warning from the Planning Wizard about constraints. |
|
#2
|
|||
|
|||
|
Right, as I said, if I change to a fixed start date it disappears. Still, that behaviour didn't occur before and previous plans were scheduled the same way.
I also don't get, why this only happens for that specific task. It doesn't occur anywhere else in the chart. One of MS Project's big miracles I'll have to live with? (I can live with just changing it to 100% when done, but still I like working with percentages) |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| what to put in to schedule for dealing with overall finish date | ketanco | Project | 7 | 10-30-2014 02:25 PM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
| Assigning finish date to work with %complete | Guloluseus | Project | 3 | 12-12-2013 10:16 AM |
how to calculate backwards from a set finish date
|
ketanco | Project | 1 | 02-07-2013 06:50 AM |
| remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |