View Single Post
 
Old 11-19-2014, 06:15 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have your project scheduled from a fixed finish date. So all of your summary tasks constraints are As Late as Possible. When added progress, I immediately got a warning from the Planning Wizard about constraints.
Reply With Quote